PROJ 592 Week 5 Assignment Problems Solution

PROJ 592 Week 5 Assignment Problems Solution


G
Asked by 2 years ago
0 points

PROJ 592 Week 5 Assignment Problems

(PROJ 592 Project Cost and Schedule Control - DeVry)

Problems 5-1 through 5-2 (Graded)

5-1 Earned Value Calculation

You are 4 months into a 6 month project. The project is linear, which means that the progress and spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going. Our accounting department has provided the following data at the end of month 4:

Actual cost to date 88,800

Planned expenditures to date 101,000

The CFO is excited and has sent you an email congratulating you for being % under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers...

PROJ 592
Guide4Students

1 Answer

G
Answered by 2 years ago
0 points

Oh Snap! This Answer is Locked

PROJ 592 Week 5 Assignment Problems Solution

Thumbnail of first page

Excerpt from file: PM592Week5AssignmentProblems PROJ592Week5AssignmentProblems (PROJ592ProjectCostandScheduleControlDeVry) Problems 5-1 through 5-2 (Graded) 5-1 Earned Value Calculation You are 4 months into a 6 month project. The project is linear, which means that the progress and spending occurs at a constant

Filename: proj-592-week-5-assignment-problems-solution-82.docx

Filesize: < 2 MB

Downloads: 0

Print Length: 6 Pages/Slides

Words: 694

Your Answer

Surround your text in *italics* or **bold**, to write a math equation use, for example, $x^2+2x+1=0$ or $$\beta^2-1=0$$

Use LaTeX to type formulas and markdown to format text. See example.

Sign up or Log in

  • Answer the question above my logging into the following networks
Sign in
Sign in
Sign in

Post as a guest

  • Your email will not be shared or posted anywhere on our site
  •  

Stats
Views: 10
Asked: 2 years ago

Related